Understanding the Grid Constraint Challenge
For many transit agencies, this scenario triggers a predictable chain of events:
- Request utility service upgrade
- Navigate complex approval processes
- Secure capital funding (often seven figures)
- Wait 12-18 months for implementation
- Hope your electrification timeline survives the delay
The TTC faced exactly these hurdles: a $1.2 million upgrade cost and a 52-week lead time that would significantly delay their electrification goals.
Quantifying the Impact
The immediate benefits were substantial:
- Utility upgrade cost avoidance: $1.2 million
- Time savings: 14 months shorter schedule
- Full fleet deployment: 36 electric buses on schedule
However, the long-term operational benefits may be even more significant. The system generates approximately $310,000 in annual value through:
- Significantly reduced electricity costs
- Demand charge reduction
- Revenue from offering energy services to the electricity grid
Download our case study below to learn more:
